Work continues on the hundreds of repairs to Tairāwhiti rural roads damaged by Cyclone Gabrielle.
Gisborne District Council says 60 slips and dropouts have been repaired and contractors remain on track to repair another 200 in 2025.
Two major Government-funded programmes of work have hit “top gear” with more than $78 million to be spent on repairing more than 600 cyclone-damaged sites over the next three years, excluding bridges, a council update says.
“Since government cyclone recovery funding was approved in October, 60 slips and dropouts have been repaired and we’re on track to repair another 200 this year.
“A total of 344 slips and dropouts will be repaired by mid-2027 and some of them are on the busiest forestry and farming transport routes.”