Following the decision earlier this year that Crown Irrigation Investments (CII) could not help fund the Central Otago Falls Dam irrigation project, Manuherikia River Ltd (MRL) chairman Allan Kane and his team are looking at other options to finance its pre-construction phase.
Following significant investigation of various options, commissioned by the Manuherikia Catchment Water Strategy Group, the decision was made to raise the level of Falls Dam by 6m and upgrade the associated infrastructure.
The proposed project would irrigate 12,500ha in the Manuherikia Valley at a possible cost of up to $30million.
Mr Kane said the group, now renamed MRL, would continue with the feasibility phase of the scheme as planned at least until the end of the year.
He said the current phase was funded following a call for expressions of interest from farmers to commit $50/ha of land they wished to irrigate. That provided about $750,000, half the $1.5million required for the current stage.