A draft report investigating Wintec's overseas spending and expenses has finally been completed at a cost of $130,000, which is $50,000 more than initially estimated.
Wintec chairman Barry Harris confirmed the council had received Audit NZ's confidential draft report and was in the process of reviewing it and providing feedback.
Once the report was finalised by Audit NZ, it would be received by the council before details on the findings would be released to stakeholders and media at the same time, he said.
The draft report has cost Wintec $129,972 excluding GST, and includes $9972 in disbursements.
It was estimated the initial audit work would cost Wintec approximately $80,000 and was to be completed within three months. It has now taken eight months to get to the draft report stage.