The intersection of Nixon and Moana streets in Whanganui East will be closed for a month as work to replace a 113-year-old wastewater main gets back under way.
It marks the start of stage two of the project, will which eventually replace a 991-metre length of pipe that runs from Anzac Parade to the five-road junction at the Raine St, Wakefield St, Nixon St, Burton Avenue and Duncan St intersection.
Stage one, which stretched from Anzac Parade to Moana St, was hampered by the state-of-the-art boring machine jamming on ancient tōtara found around eight metres under the surface.
The timber, along with poor soil quality, ate through time and budget and required unbudgeted funding worth $1.5m to be signed off by the Whanganui District Council to get the job finished by 2024.