With just two weeks until the completion date of December 20, Waka Kotahi says it’s making good progress on Coromandel’s new State Highway 25a bridge.
Last week the team finished the soil nailing which stabilises the slip-face, Waka Kotahi said.
“They are now completing the grouting getting the mesh in place and bearing plates on the slip face.”
The pavement on the western road approach was finished and the kerb channel and transition side barriers between the road approach and the bridge were installed.
On the eastern approach, precast stormwater u-channels were now in place and the slope above the southern side of the road was hydroseeded.