The $55 million machine has doubled as a subterranean factory, lining the tunnels as it went with more than 24,000 prefabricated concrete segments, each weighing about 10 tonnes and churned out of a batching plant in East Tamaki which has already been decommissioned.
It has been trailed both ways by an expanding conveyor belt which has carried about 800,000cu m of spoil out of the tunnels to a drying plant, for transfer by trucks to a disused Wiri quarry.
That included a 180-degree turn in a tight space at Waterview, where 200 litres of sheep's lanolin was used to ease the various segments of the tunnelling machine around the bend.
The Transport Agency says more than 800 staff and contractors on the $1.4 billion project will stop work this morning to watch video of the expected breakthrough in a marquee above the southern approach trench at Owairaka. But it says its priority is for the operation to be conducted safety and effectively, so neither the time nor even date of the breakthrough can be guaranteed.