The largest concrete pour within the Christchurch central city cordon so far began at 3am on Thursday 28 February, and took 13 hours to complete. This timelapse shows the almost-750 cubic metres of concrete being laid on the site of a new four-storey office building on the corner of High and Lichfield streets. There were 32 trucks and two pumps were needed for the project as well as a team of 19 staff.