Aerial photograph of the Northern end of the Waterview Connection in Waterview. Photo / Richard Robinson
Aerial photograph of the Northern end of the Waterview Connection in Waterview. Photo / Richard Robinson
Auckland's $1.4 billion Waterview Connection is under way, and by early 2017 will help provide drivers from Manukau to Albany with an alternative to State Highway 1 and the harbour bridge.
The 4.8km link between the Southwestern and Northwestern Motorways will fill the last-but-one gap in the 48km Western Ring Route. It will bypass the city to the west and link Manukau, Auckland, Waitakere and North Shore.
All that will be left to complete, by about 2019, will be a $500 million-plus motorway-to-motorway interchange at the northern end of the route.
As one of the world's largest tunnelling machines burrows below Oakley Creek on its 2.4km journey from Owairaka to Waterview, a three-level traffic inter-change is starting to sprout up as Spaghetti Junction II beside the Northwestern Motorway.
Work is also gathering pace on $475 million worth of associated projects along the Motorway.
These include widening almost 9km of the Northwestern from St Lukes to Te Atatu, while raising the 4.8km motorway causeway across an inlet of the Waitemata Harbour and Whau River.
Motorway interchanges are being upgraded at Lincoln Rd in Henderson and at Te Atatu, to be followed soon by a duplication of the St Lukes Rd bridge over the Northwestern at Western Springs.
Waterview Connection Link between Southwestern and Northwestern Motorways
Length: 4.8km (half of it tunnelled) Cost: $1.4 billion Completion: early 2017
Waterview components
Twin tunnels Three lanes in each direction
A tunnel boring machine had by yesterday dug 744m of its 2.4km way north to Waterview, from where it is due to break out of the ground in September, before being turned around to burrow back to Owairaka. It is being tailed all the way by an enclosed conveyor belt which has removed about 122,000cum of soil to a drying plant. The machine has lined the tunnel with about 368 pre-cast concrete rings, to a maximum depth so far of 34 metres.
1. Southern end of tunnels
Photo / Richard Robinson
2km of surface road is being developed through Alan Wood Reserve and Hendon Park from the end of the Southwestern Motorway at Maioro St, New Windsor, where an interchange is being enlarged to feed traffic to and from the new tunnels, under the new Richardson Rd bridge.
The road sinks into a deep trench, from which the $54 million boring machine began its journey in November.
Six southern spans have been erected for a footbridge over the surface motorway section in Hendon Park.
Excavation of a 25m-deep exit and approach trench has almost finished, and base slabs are being laid.
Large portal frames are being formed, ready for the boring machine to pop out of the ground in September.
Preparations for building a traffic emissions venting tower 120m on the other side of Great North Rd from the tunnels have been completed, and piling for the15m structure has begun.
Great North Rd has been looped for the first half of the tower before the road is straightened temporarily to make way for the boring machine, and then rediverted to complete the tower.
A big yellow gantry is installing beams over Great North Rd's approach to its existing interchange with the Northwestern Motorway, to form one of four new ramps feeding traffic in and out of the tunnels.
A large earth embankment has already been formed to carry traffic between the ramps and tunnels.
Large retaining wallsare being built from the future interchange to the east of the Carrington Rd bridge over the Northwestern Motorway.
Causeway being widened and raised by 1.5m to provide extra traffic lanes and prevent flooding and to stop debris from washing over the motorway at spring tides.
152,000 tonnes of material including quarry stone has been loaded on to a reclamation on the seaward side of the causeway to compact the ground before new eastbound traffic lanes can be laid late this year. Traffic will then be moved on to the new structure, to allow existing lanes to be raised for westbound traffic.
New westbound on-ramp from Great North Rd has been completed.
Includes widening the motorway to four lanes each way and broadening the St Lukes Rd interchange bridge to Western Springs to three lanes each way, plus a shared cycle-walkway.
7. Lincoln Rd interchange
Photo / Richard Robinson
Cost $135m Completion June 2015
Work began in late 2010 and is about 75 per cent complete.
New seven-lane Selwood Rd bridge has been built over the motorway to replace the old two-lane structure.
Time-lapse video showing progress through June to prepare the Southern Approach Trench in Owairaka for the arrival of the TBM and subsequent start of tunnelling ...
Video Player is loading.
Current Time 0:00
/
Duration 0:00
Loaded: 0%
0:00
Stream Type LIVE
Remaining Time -0:00
1x
Chapters
descriptions off, selected
captions settings, opens captions settings dialog
captions off, selected
This is a modal window.
Beginning of dialog window. Escape will cancel and close the window.
End of dialog window.
This is a modal window. This modal can be closed by pressing the Escape key or activating the close button.
Tauranga garage fire
UP NEXT:
NOW PLAYING • Timelapse: Waterview Connection progress
Time-lapse video showing progress through June to prepare the Southern Approach Trench in Owairaka for the arrival of the TBM and subsequent start of tunnelling ...
Read more on the Waterview Connection plans on the NZTA website.