It cost $290 million to develop but - almost five years after it was ripped apart by a deadly explosion - the Pike River Mine site has been dismantled bit-by-bit as the Department of Conservation waits to resume ownership of the site. The site is expected to be handed to DOC shortly.
Environment Minister Nick Smith is also expected to announce a memorial "Great Walk" dedicated to the 29 men who died in the explosion, about the time of the fifth anniversary of the disaster on November 19.
Although $290m was spent on mine development, just a month before the November 2010 disaster the Pike River Coal Company was facing potentially $50m in extra costs.
After the disaster, Solid Energy purchased the mine in July 2012 for just $7.5m.
Solid Energy legal services manager Rob Paige said the coal processing plant deconstruction was being done by the purchaser.