Concrete is set to be poured as work continues at the State Highway 25A Taparahi bridge construction site.
Waka Kotahi New Zealand Transport Agency said the team faced a challenging start to the week with the bad weather, but managed to continue placing the pre-cast deck panels, drill soil nails to stabilise the slip face and complete the earthworks at the eastern approach to the bridge.
“By last Sunday, 70 pre-cast panels had been installed. As the panels are put in place, they are ‘stitched’ together with steel reinforcement and concrete. Our steel fixers have already begun putting in the reinforcement, and the first of three concrete pours is scheduled for early this week.
“The first of two new drainage road crossings was completed, and one of the 100T cranes was also demobilised as it is no longer required.