Napier Port has had a busy few days, unloading and trucking 16 turbines down to Mercury Energy's new wind farm in Manawatū.
This is the first of what is likely to be four shipments of similar size as a total of 60 turbines are erected on the hills at Turitea in Manawatū.
When completed, it will form New Zealand's largest wind farm by output at 222MW, producing 840GWh annually (enough to power 375,000 electric vehicles).
The ship is carrying 32 tower sections, 16 nacelles (casings), 16 drivetrains and 16 hubs, plus associated accessory parts – everything you need to construct 16 wind turbines (apart from the blades and a lot of concrete).
The blades were shipped to Port Taranaki.
The heavy equipment was unloaded by crane with specialised heavy haulage rigs, before being moved to Onekawa where they will be stored before being transported to Manawatū later this autumn.
SSA New Zealand, formerly known as Southern Cross Stevedores, is moving the massive cargo and Gareth Jones was the one making sure it all ran smoothly.