Documents released under the Official Information Act have revealed a major steel failure on a Waikato highway.
Emails between NZ Transport Agency managers and contractors for the Huntly section of the new Waikato Expressway revealed the bridge file castings were found to be substandard and had 600 huge steel-rod fails.
This was shortly before the Fulton Hogan-HEB joint venture.
Agency senior project manager Kevin Johnson told another manager in an email that these were to be used as "piling and structural support for bridges, flyovers and various structural elements".
The 12m-long, 450mm diameter rods were imported from China.