Detailed reports on the future of Christchurch's stalled stadium have been made public -including the successful negotiation of fixed-price contract for its construction.
And it has emerged that if the project is stopped, $40 million in "sunk costs" will be lost entirely and the budget will rise further if there is any pause on the build.
The Christchurch City Council today confirmed the total budget for the project will sit at $683 million.
Rates in the city will need to increase by 1.24 per cent to cover the cost of what the CCC will need to borrow to fund the project.
But that rose to $533m, and in recent months the Christchurch City Council revealed the proposed design for the stadium, Te Kaha, had blown its budget again.
The cost then spiked to $683m - with the $150m increase being blamed on rising international costs in materials and construction.
The price hike sparked a public consultation last month and the CCC received 30,000 public submissions about the project.
Of those, 77 per cent of people were in favour of meeting the extra costs.
A further 8 per cent supported a pause and re-evaluate approach and 15 per cent wanted a complete halt to the stadium's construction.
Councillors will decide on the stadium's future at a meeting on Thursday morning.
The options are to invest the additional $150m to enable the project to continue as planned, stop the project altogether or pause and re-evaluate it.
Today the design and construction submission for Te Kaha - on which councillors will base their decision - was revealed.
Te Kaha Project Delivery Limited chairman Barry Bragg said today that a "major issue" had been that the lead contractor BESIX Watpac had been "unwilling" to provide a fixed price "because of the volatility in the commodities market".
"We were concerned that would leave the council and the ratepayers of Christchurch exposed to the risk of further cost escalations and that is not something we were willing to accept," Bragg said today.
"The board has been working through the risks with BESIX Watpac and they have now submitted a revised design and construction submission that provides a fixed price.
"The Board has thoroughly reviewed the new submission and obtained independent legal advice on it.
"It is now in a position to make a recommendation to the council that it enters into a Design and Construct contract."
Bragg said based on the new contract he was confident the arena could be delivered for a total budget of $682 million.
"That figure includes sufficient contingency to cover any issues that might emerge during the build," he explained.
"The fixed price means that if the council decides on Thursday it wants to proceed, ratepayers will be protected from any further cost increases."
Te Kaha will have a capacity of 30,000 and will be used not only for sports matches but concerts, trade shows and expos.
Last year, the council decided to slash the stadium's capacity by 5000 to 25,000 in response to the rising cost - then did a U-turn after a public outcry.
Thursday's council meeting where Te Kaha will be discussed before councillors vote will start at 10am and will be live-streamed via herald.co.nz