Q: Many millions were spent by NZTA building SH20, to the current run off at Maioro St.
In the past few months the road heading north from Dominion Rd to Maioro St has been ripped up, extra construction added to the left side and the road moved over, leaving a very rough road surface.
It also appears they are building more strengthened barriers in the middle between northbound and southbound traffic.
Why is all this taking place, when the initial construction appeared so good?
Allen Grainger, Auckland.
A spokesman for the Transport Agency says all the work under way around Maioro St is part of a staged construction programme spanning several years to accommodate the development of other projects along the Southwestern Motorway. These projects include the Mt Roskill extension, the upgrade of the Maioro St interchange (replacing the old roundabout with the present bridge), and the Waterview tunnels.
There will be an extra northbound motorway lane, and the existing off-ramp lanes are being moved further left to allow traffic to head towards the tunnels safely. The Transport Agency says doing this work earlier and leaving it unused for a long time would have been uneconomical and unsafe.