Winter is when we're reminded how some areas of the section can get boggy. But you don't have to stand for the mud. Take these practical steps, whether it's for a courtyard, a path to the clothesline or something more ambitious.
Step 1 - Excavate and remove the topsoil to about 150mm deep, or down to hard clay.
Step 2 - Set up string lines tied to stakes at either end of the area to be paved, at the height you want to pavers to sit at. Allow for a fall of at least 10mm per metre sloping towards a drainage point. Use a level to help.
Step 3 - Fill the excavated area with gap 20. Rake out and screed the area to about 60mm below the string line. Compact the base thoroughly.