The New Zealand Transport Agency has given the joint venture building the $850 million Transmission Gully motorway north of Wellington some breathing room on its completion date after the November 2016 earthquake, followed by torrential rain, held up the project.
The joint venture between CPB Contractors and HEB Construction building the 27-kilometre, four-lane highway updated its programme last year to include delays from those events, saying if the time impacts weren't approved by NZTA and the public-private partnership contractor, Wellington Gateway Partnership, then the April 2020 opening date could get pushed out further than anticipated, to August 2020.
The PPP contract has provisions for the contractor to seek relief if construction is hindered by events outside its control, subject to independent reviewer Aurecon New Zealand's approval. Those terms allow for an extension to the start date, or NZTA covering the change in costs.
NZTA senior manager project delivery Chris Hunt told BusinessDesk in an emailed statement the contractor sought relief for minor on-site delays as a result of the quake and flooding, which the government agency put to the independent reviewer.
"The independent assessment concluded that 20 additional days will be required to complete work on Transmission Gully as a result of these events," Hunt said. "The New Zealand Transport Agency has accepted this time extension."