Marmite lovers can breathe a sigh of relief with the news that Sanitarium's earthquake-damaged Christchurch factory should be given the all-clear by Christmas.
Marmite has been in short supply since the Papanui plant was shut down by the Canterbury earthquakes, with the situation being dubbed "Marmageddon".
Christchurch City Council building inspectors were at the site today to see whether it could get a code of compliance, and determined one could be issued by Christmas.
Building operations unit manager Ethan Stetson said there was an issue with an unfinished lift, which would not be completed until 2013.
However, the council was endeavouring to work around this and would handle the lift as its own distinct consent.