Fletcher Building’s chief executive is willing to take insurers to court over a $105 million unpaid claim to repair the troubled New Zealand International Convention Centre for SkyCity.
Speaking to Markets with Madison, Ross Taylor explained the excess still on the table - which was about one-third of the $255m extra required to finish the now $1 billion project by the end of 2024.
“The Convention Centre’s really frustrating. While I think we’re doing a good job to finish it off, it’s still hurting everybody - the business, the shareholders.”
Taylor said the project was absolutely unprofitable. It was delayed by around six years, although he’d lost exact count.