Fletcher Building is being sued for $7.5 million by utilities contractor Electrix, one of the subcontractors on the Christchurch Justice and Emergency Services Precinct.
The project was one of several that contributed to $1 billion of losses for Fletcher's Building + Interiors unit over a two-year period. It finally opened in September 2017.
The High Court at Auckland heard today how Electrix had worked on the project for more than three years and was paid approximately $21m. However, it claims it should get another $7.45m for work that it did.
The case, set down for several weeks, will shed light on what happened with the multimillion-dollar project which caused losses to Fletcher's building and interiors unit.