A Court of Appeal win for a Christchurch company which dug up a carpark over a $300,000 payment reinforces the importance of clear communication in arrangements with subcontractors, says one of the country's leading law firms.
Otherwise, says Chapman Tripp, a court can take the matter out of the parties' hands.
Complete Siteworks Company was a subcontractor in a Christchurch supermarket carpark project and between July 2013 and January 2014 issued four late payment claims to head contractor Watts & Hughes.
While Watts & Hughes had the discretion under the subcontract to treat these claims as if they had been received the following month, it dealt with them as if they had been submitted by the due date.
However, the next payment claim in February 2014 was also late and while Watts & Hughes again could treat it as if it had come in the following month, it did not tell CSC it intended to do this.