A project to replace the Pekatahi Bridge deck on State Highway 2 in the Eastern Bay of Plenty has reached the half-way point, the NZ Transport Agency says.
The one-way bridge between Awakeri and Taneatua was closed to traffic in early February to allow contractors to replace the deteriorating timber deck and remove the existing railway tracks.
Traffic is being detoured via Whakatane while the project is underway. The detour adds about 20 minutes to the journey between Awakeri and Taneatua, with longer delays possible during peak periods.
Transport Agency Bay of Plenty highway manager Niclas Johansson said the project was progressing well and was on track to be finished in May as planned.
"Over the last six weeks the contractor, Downer Construction, has removed the rail tracks, deconstructed the old timber deck and re-decked about 35 per cent of the bridge," Mr Johansson said.