Work to complete the upgrade of the old City Focus, now named Manawa, has been delayed, but through no fault of the council or its contractor.
Rotorua district councillors were updated on the project at a meeting of the Rotorua Lakes Council today.
They were told the final construction phase would not start for at least another three weeks due to the contractor taking on emergency work in the flood ravaged township of Edgecumbe.
Earlier this month, the council signed off on the final phase of the upgrade that was supposed to start early next week and be finished mid to late July.
The contract to complete the $1.36 million upgrade, that will see the area opened up to traffic using both Tutanekai and Hinemoa Sts, while also accommodating the council's Green Corridor cycleway and pedestrians, was given to Fletcher Construction.