Cobblestones removed due to the redevelopment of the old City Focus will almost all be reused in Manawa - Heart of the City - by the time work is completed.
The final stage of redevelopment work began a few weeks ago with both roads into the area closed off by contractors with fencing and road closure signs up around the Hinemoa and Tutanekai Sts intersection.
According to the Rotorua Lakes Council, the design was aimed at improving vehicle movement through the intersection, clearing sight lines in all directions and ensuring a focus on people, enabling better use of the space.
It is the third and final stage of redevelopment of the area with the project approved following feedback from inner-city stakeholders and the community.
Fletcher Construction agreed to a fixed price of $1.135 million for the third stage.