Construction on the new Rotokauri Transport Hub has resumed after the Covid-19 lockdown and expected to be completed at the end of October.
The timing meets the proposed November launch date of the new Hamilton-to-Auckland passenger rail service.
The new hub, which will include a park and ride, rail station, bus interchange and pedestrian connection to The Base, will also be a key interchange for the new rail service.
Councillor Ewan Wilson, Hamilton City Council's representative on the rail governance working group, says restarting the project, and initiating the start-up passenger rail service, is an important step in supporting the local and regional economy.
"The council and its contractors have done everything possible to maintain momentum on key projects in recent months. This new service isn't just about safer transport options, it's also about offering social and business connections and another boost to domestic tourism which will play a huge part in our country's economic recovery post-Covid-19," Mr Wilson said