The construction of a viaduct bridge at the damaged SH25A Taparahi site is well under way with work above the ground started and the first two structures visible at Pier B.
Waka Kotahi has provided a progress update:
Abutment A and D: We poured the blinding concrete at Abutment D and have landed both Abutment A and Abutment D reinforcement cages. The team is now fixing and forming the cages for our first abutment pour later in the week.
Pier B: Concrete pile pours at Pier B were completed, which included our deepest pile to date - 41 metres. This is double the depth of the other piles (about 22 metres deep). These piles have already been cropped and undergone integrity testing. The team has started installing the column cages for the bridge, two of four have been installed at Pier B. We can now see the structure appearing out of the slip floor (as per the photo).
Pier C: We completed the working platform at Pier C and moved our piling rig into position. We’ve drilled out the four piles and poured the first one today. Once we’ve finished the remaining three pours this will mark the completion of the Taparahi bridge piling activity. This means our piling rig and crew will be demobilising and head off-site to another project.