The final girder has been lifted into place as construction continues on State Highway 25A’s new bridge.
Waka Kotahi said the beam was lifted into place on Wednesday, October 18 – just 10 days after the first was installed. There were three steel girders per span and these were formed from 15 sections in total bolted together.
The next challenge for the team was forming the deck surface with 138 pre-cast reinforced concrete deck slabs and installing 44 precast side barriers.
To get this into scale these slabs, and the concrete poured in between them, would weigh over 1000 tonnes. The barriers would be placed over these and a levelling and asphalt layer would be laid.
In total, the steel girders would support 1560 tonnes of concrete and asphalt before traffic went over the bridge. This huge load (and the weight of the girders themselves) made the girders bend and to avoid a roller coaster effect as you drive over the bridge the girders were built with a slight arch profile. This was carefully worked out by the designers and carefully built in by the fabricators, Waka Kotahi said.