Waka Kotahi- NZTA has provided an update on their contractor’s progress at the Taparahi State Highway 25A bridge site, which includes the insertion of giant piles.
Damage from Cyclones Hale and Gabrielle aggrandised an earlier 60-metre gap in the road caused by the Auckland Anniversary Weekend flooding to about 110 metres, and the destruction cut off access to the eastern Coromandel Peninsula at the summit of State Highway 25A at Taparahi, around 10km from Kopu south of Thames.
Up to 100 contractors are working over a 20-hour-a-day cycle on the project, aiming to meet a March deadline. The total cost is expected to be around $50 million, at least $10 million more than the $30-40m figure quoted by Waka Kotahi in May this year.
Piles have been driven down to support the bridge 21-24 metres deep into the hillside where they’re secured to solid rock.