Genesis Energy said an outage at its Unit 5 combined cycle gas plant at Huntly would cost $20-$30 million.
Unit 5, which usually delivers continuous or baseload power to the electricity grid, has been out of action since June 30.
An investigation revealed a failure of one of the unit’s three circuit breakers.
Specialist parts, including some from overseas, are required for repair, the company said.
Genesis had earlier advised that it expected Unit 5 to return to service by August 31, but it has now pushed that date out to May next year.