Toll waivers on the Tauranga Eastern Link have been extended with wild weather delaying "vital" Te Puke Highway riverbank works.
The country's transport agency said strong winds had impacted the capacity to safely complete work to stabilise the Kaituna riverbank alongside the Te Puke Highway and extra time was needed to complete the job.
Waka Kotahi NZ Transport Agency infrastructure delivery regional manager Jo Wilton said while the team had made significant progress, getting the crane into position safely and some very windy conditions affected the programme.
"Well over 50 per cent of the sheet piles are in place, however, we need a bit more time to complete the retaining wall.
"The weather slowed things down this week as the crane can't operate in high winds. The 20 metre steel sheet piles act like a big sail, and that's not safe for anyone."