Tauranga ratepayers face a $7 million-plus bill to demolish a defect-riddled central city carpark building but dodged a catastrophic failure.
The structural designer of Harington St Transport Hub, a 550-space carpark building, said it blew the whistle on itself.
But the city council rejects that.
It has launched legal action against the designer and "others" it has not named, and lodged official complaints asking for action against three engineers.
It has been advised the best option is to limit losses to about $27m all-up by pulling down the Harington St Transport Hub block, versus spending $65m rebuilding it, according to documents newly released to RNZ.
However, council infrastructure manager Nic Johansson sweats an even worse outcome.
"Someone might have had the attitude that 'she'll be right' and carried on," he said.
"We could have ended up with a completed building that would have worked and looked quite fine until there was a seismic event, and it could have been a catastrophic outcome."
The documents show a litany of floor, column and bracing weaknesses that have deterred the council - and contractors - from wanting to even try to remediate the building.
They include foundations so thin they needed another 300 tonnes of reinforcing steel and 140 truckloads of concrete, eight columns that needed destroying using hydro jets, to rebuild, while propping up floors above, welds missing between plates and ungraded steel in key brace connections.
A multi-storey build unravels
The carpark building, commissioned at $29m to boost the city centre, was already 20m out of the ground in March 2019, when a concrete pour went ahead - and a beam twisted.
The whole project then began to unravel.
At that stage, "two-thirds of the structural steel had been erected and half of the concrete elements completed", the documents said.
"Whilst not expressly stated at the time, it became apparent that the issue related to the seismic resilience of the building."
That took months to come to light - initially, the council believed the defects were few and isolated.
The building's designer, veteran nationwide structural engineering company Harrison Grierson, did a review, told the council there was "an issue with the ramps", made some localised design changes, and the council issued another consent in July 2019.
Harrison Grierson's managing director Glen Cornelius claimed to RNZ that his firm blew the whistle on itself.
"It was Harrison Grierson who identified and advised the council that a remedial design was needed for the building," Cornelius said in a statement.
Johansson was non-plussed at that claim.
"I struggle to understand that statement," he said.
It was the builder, Watts and Hughes, that raised the alarm and responded well, he said, leading to what proved to be a vital decision by the council to call in outside assessors, at the same time as Harrison Grierson was amending its original design.
"We were starting to lose confidence," Johansson said.
"We had specialists on site and it became obvious there weren't seismic [proof] joints between the ramps and the floor slabs.
"There were real doubts about the design principles and the fundamentals."
As for Harrison Grierson, "it was only in August that it was recognised by them" just how big the problems were, he said.
Complaints against engineers
A full halt to construction was called in September 2019.
Costs to the council carried on, at $4000 per day - not accounting for the loss to Tauranga of extra carparking.
By then it was clear that parts of the site, like the stairwells, were not safe to work around, though seismic forces were not in play in the same threatening way as they would be were the building actually finished with its full loading on the walls, Johansson said.
The council has now lodged official complaints asking Engineering New Zealand to take action against the two original designers.
The council said those two had since left Harrison Grierson.
It has lodged a third complaint against the engineer who approved the design in an independent peer review done at a small engineering company, Constructure.
Constructure founder Cory Bedford, of Christchuch, would not go on tape but told RNZ "the peer review Constructure undertook is a public issue and Constructure is responsible for that".
They were in discussions with the council, Bedford said, adding "I'm not comfortable on stating anything further to you", and referring RNZ to his lawyer.
Constructure's website says it has completed 11,000 projects in 12 years, 9000 of those in Canterbury - and 10 award-winning; in 2015 it had 18 staff, and now has 26.
Both Constructure, and Harrison Grierson said they had undertaken internal reviews of what went wrong but rejected the need for independent review.
"Our internal review was undertaken by senior Harrison Grierson personnel who were not involved directly with the Harington St Transport Hub project to ensure their objectivity," Cornelius said.
"The review considered where the issues were, how they came about and what Harrison Grierson can do to ensure this doesn't happen again."
The problems were confined to the carpark, and did "not reflect the depth of expertise and standard of service we set ourselves", Cornelius said.
Harrison Grierson employs several hundred people and has been in business 130 years.
'Hate for anyone else' to go through this
The council abandoned the project formally two months ago.
It was "tortuous" getting to that point, Johansson said.
"Removing and replacing a ramp that is tied to the basement floor requires considerable demolition and planning to complete safely," Watts and Hughes told the council.
"Both basement wall strengthening, ramp removal and replacement see large steel beams and columns being removed and re-fitted.
"The waterproofing of fixings through the exterior precast walls poses risk and no guarantee has been given or obtained for these works based on the design."
The durability of the carpark was not even looked into, Aurecon said in June.
Demolition was very likely, the council told RNZ.
Its advice was that if it rebuilt or strengthened the block, then hiked carparking rates to try to recover costs, this would be a bad option, especially with Covid disrupting carparking demand, the documents show.
A rebuild would be so noisy - and dusty - it would probably break council noise control rules.
"I hope everyone that is involved in the sector sits up and takes notice," Johansson said.
"I would hate for anyone else to end up with a ... $27m dollar hole."
Can't 'check the checker'
Construction monitoring at the carpark building did not pick up the design faults early on.
Also, the council did not spot them when it consented the flawed design.
But there was a limit to what checks could be done, Johansson said. Hiring a "checker to check the checker" was not how the system worked, and it would be better if the industry simply lifted its game.
"The council has every right to rely on the engineering expertise from those designers that have got the right qualifications and quality marks around it," he said.
"Councils simply don't hold the expertise of going into the degree of check," it would require to review engineering designs in-depth.
Public confidence in the council's building department was badly shaken by the debacle of the Bella Vista subdivision three years ago, where consenting failures doomed 21 homes. However, this was entirely different from Harington St, Johansson said.
OIA documents released to RNZ showed the city council's building control team passed its latest accreditation test from the Ministry of Business, Innovation and Employment in September 2019, without any "serious" faults being found.
However, twice as many "moderate" faults - 26 - were found than at its previous assessment.
It was told to fix these by early 2020, MBIE records showed.
The building team had 11 unfilled technical jobs, about a quarter of its complement.
The bills from trying to rescue the afflicted carpark continue to mount; the documents show about $2m is set aside in case any construction is needed at it this year.
The council might consider compensating neighbouring apartment owners who've had to put up with it.
"It's an incredibly time-consuming and costly problem, and also frustrating to us as an organisation and our community, because now we have an eyesore sitting there much longer than it should be," Johansson said.
"It should have been a functional building being a great asset and amenity for the community."
Someone could still buy the site as-is, and negotiations and legal action could claw back costs, Johansson said.
RNZ asked if the council was checking other designs. It said another project, a small retaining wall designed by an engineer who worked on the carpark design, was being checked for compliance.
However, it is not reviewing the whole Harington St debacle.