New images of the yet-to-be-completed Tauranga tidal stairs offer the first glimpse of the $2.8 million project four months into construction.
Drone images released to the Bay of Plenty Times have captured the ongoing work on the waterfront development by The Strand.
The facility includes 49 metres of tidal stairs, a new 27m pier and a new 24x3m floating pontoon.
So far 1500cu m of Mudcrete had been used with 128 precast units making up the tidal stairs. Twenty precast units - weighing 0.5 - 10.5 tonne) have been installed per day.