Last weekend KiwiRail staff and contractors replaced two railway bridges - Bridge 105 near Pukehina Beach Rd and Bridge 91 just outside Te Puke.
"In order to minimise the disruption to our freight customers, we replaced both bridges over the same weekend,'' says KiwiRail chief operating officer, capital projects, David Gordon.
"Freight train services did not run between Te Maunga and Kawerau on Saturday and Sunday.
"We originally planned to do this work during Easter, however, the Covid-19 lockdown period meant we had to reschedule.
David says the old timber bridges had reached the end of their useful life and have now been replaced with modern concrete bridges.