Work to get a temporary road in place around the State Highway 4 slip is progressing with contractors undertaking drainage and revegetation work at the site.
Now NZTA says it expects a temporary road could be in place early next year.
The Parapara road has been closed since early October after it was significantly damaged by a major slip.
Crews moved onsite last week after testing confirmed it was safe for contractors to work on the slip face.
Although the site is still vulnerable to further slippage, especially in heavy rain, recent geotechnical assessments have given NZTA confidence that the construction of a temporary road can begin.