The Sarjeant Gallery redevelopment is well under way and both stages of the project are progressing steadily.
On the roof of the 100-year-old Sarjeant Gallery building, core drilling for post tensioned steel bars that will create a virtual cage within the double brick cavity walls is 90 per cent complete and insertion of the steel bars is under way. Once inserted, the bars will be held in tension by a new concrete capping beam at roof level and the concrete foundations at the basement level.
Inside the building, excavation and construction of the ground beams and new concrete foundations is steady but slow, given the fragile condition and variable depths of some of the existing foundations. Insertion of sheet piling to support the walls and existing foundations is nearing completion in the east and is progressing under the building's central dome.
Ground beams and floors are being poured in sections in the west wing where reinforcing is being tied and boxing placed against the old walls ahead of pouring concrete. This will increase the width and strength of the walls in the basement.
Meanwhile, in the new extension wing, Pataka o Sir Te Atawhai Archie John Taiaroa, construction of the underground basement is progressing well with ground beams nearing completion and pouring of the basement floors, walls and columns currently at 50 per cent.