The restrictions of Covid-19 have disrupted construction projects nationwide including the new $8.2 Bulls Community Centre.
But with contractors able to return to the site when New Zealand moved to alert level 3, the project is now 90 per cent finished.
Construction of the Rangitīkei District Council project, situated on the corner of Criterion and Bridge streets, began in December 2018 and the council says its major construction works are due for completion by the end of July.
There will then be a fit-out and moving in period in September before it opens to the public.
The council's executive office manager, Carol Gordon, said W&W Construction and key subcontractors are working hard on finishing off the lighting, painting and other trades.