Waka Kotahi NZ Transport Agency reported "significant progress on repairing State Highway 1 past the major remaining slip in the Mangamuka Gorge.
The installation of steel and concrete piles to support the road above the slip had been completed. The road was opened to holiday traffic for three weeks over Christmas, and closed again on January 10 so work could resume, since when another 16 piles have been drilled, completing the 49 required to support and ensure the long-term safety and stability of the road.
"It's been a great effort by the drill crew, but this is just Stage 1 of the repair, and there's still a lot more work required before we can open the road to traffic again," Northland system manager Jacqui Hori-Hoult said however.
The next stage would be to install capping beams that would add to the stability of the pile wall. They would be attached to the top of each pile with supporting cables drilled into the bank under the road. Once the road was rebuilt, the capping beams would be part of the road substructure.
Work had also begun on cutting into the bank above the road to widen and restore the road past the slip to two lanes.