Construction work has begun at Sweetwater, where the Far North District Council plans to develop a bore site to supplement the Awanui River, its main source of water for Kaitaia.
McMillan Drilling is currently sinking a production bore, which will be followed by two monitoring bores within the next couple of weeks.
The next project milestone, due in November, will be the appointment of a main contractor to complete the project, including building a pipeline from the bore to the water treatment plant in Okahu Rd, in Kaitaia.
Water is scheduled to begin arriving from the aquifer before the summer of 2021/22.
Meanwhile the council says a back-up water supply for Kaikohe could be operational before Christmas. It plans to establish a second, 120m bore at Monument Hill to access a more sustainable supply of groundwater, with drilling and testing to confirm water quantity and any impacts on surrounding groundwater sources expected to begin within weeks.