Far North District Council receives government subsidy for road maintenance of approximately 55 per cent, whereas the storm damage subsidy for the recent storm event is 95 per cent (normally in 80-95 per cent range).
So it seems to me, staff think it is better to repair slips after a storm event and capture the higher subsidy.
This sounds sensible, until you think it through and do the maths.
The Mangakahia road slip could have had maintenance work to have the toe secured to prevent the recent major road failure at a cost estimated at $50,000. Government maintenance subsidy 55 per cent = $27,500, required ratepayer funding $22,500.
The major slip currently being repaired could cost $1 million. Government storm subsidy 95 per cent = $950,000, required ratepayer funding $50,000.
So by not maintaining the road to prevent the slip, the ratepayer is $27,500 worse off, plus the access disruption and economic loss to the Far North, Northland and NZ must be factored in.
This is estimated at in excess of $1 million/day as milk was dumped, logs, meat and other produce not harvested, many off work, and firms contracted to deliver fuel, produce or maintain business interests had to carry costs of the lengthy detours.
With the recently released FNDC annual plan, produced by the current council governance group, showing debt will rise from $81-$98 million at June 30, 2015, I wonder how they intend to cover the extra storm damage costs. More debt to cover the ratepayer share or rate increases?
It seems the same thinking affects our highway network staff and contractors, with slips closing State Highway 1 at the top of Waiomio and the Brynderwyn Hill. More on route security later, what we need now is a maintenance strategy.
Steve McNally Acting board chairman, Focus NZ