Contractors made the most of the days between Christmas and New Year to construct a rail underpass for the Kamo Shared Path in Whangārei.
The concrete underpass, which is still heavily fenced off, has been built behind properties on Fisher Tce in Kamo.
While the first two stages of the path from Rust Ave to Kamo Rd were officially opened in December, work to continue building the rest of the path has continued.
The underpass is part of stage four of the path from Adams Place to Fisher Tce. The stage is planned to be finished around the middle of the year.
Work on the $4.5 million stage three - from Kamo Rd to Jack St - has started and is expected to be finished around May this year.