Work is progressing on the new two-lane bridge at Taipā, in the Far North.
The NZTA's latest progress report on the new State Highway 10 bridge at Taipā said piling of the temporary staging from which the new two-lane bridge will be built is nearing completion on the eastern side of the river.
The first of three pier headstocks was under way, and causeway earthworks on the western side were almost finished. The causeway now extended as far as it would reach into the river.
Plans are being made to relocate services such as communications, water and wastewater, with stormwater works programmed to begin in around six weeks, following the relocation of the existing wastewater pipe. A new stormwater pipe will be laid from Oruru Rd, through the carpark and alongside SH10 as far as Taipā Area School.
This week the smaller crane and drill rig would be moved from the western (township) side of the river to the east side. That means temporary restrictions to traffic on
Oruru Rd and around the parking area at the shops.