Work on slips that blocked State Highway 1 through Mangamuka Gorge in Northland is progressing, but there's still a lot more needed to get the road open again.
Waka Kotahi NZ Transport Agency said there has been significant progress on repairing SH1 past the big slip in the gorge. The installation of steel and concrete piles to support the road above the slip has now been completed.
The slips closed the road during a massive storm in July that dumped more than 220mm of rain on Northland in a few hours.
The total estimated cost of the Mangamuka Gorge repairs is $13.8m. This includes the ongoing slip repairs and the cost of the initial emergency response to last July's storm damage.
The road was opened to holiday traffic for three weeks over Christmas and closed again on January 10 so work could resume. Since then, another 16 piles have been drilled, completing the total of 49 required to support and ensure the long-term safety and stability of the road.