The Far North District Council and the Northland Transportation Alliance have built almost 3km of new footpaths, at a cost of $767,500, in the Far North this financial year, part of a $2 million capital works and renewals programme for paths.
The new paths have been laid on Mangakahia Rd, Kaikohe (201m), Mangakahia Rd (toward Carey Rd), Kaikohe (111m), Rangihamama Rd, Kaikohe (741m), Greenway Dr to Aranga Rd, Kerikeri (565m), Long Beach Rd (footpath corner to carpark), Russell (68m), Mission Rd, Kerikeri (680m), and Donald Rd to Hillcrest Rd, Kaitaia (395m).
Construction has also started on 795m from North Park Dr to Whangatane Dr, Kaitaia, and 477m on Tau Henare Dr, Waitangi.
Far North Mayor John Carter said the new paths built this financial year exceeded the total delivered for each of the previous three financial years.
"We are delivering more each year," he said.