The Hawke's Bay Rugby Union doesn't see any need yet for contingency plans if McLean Park is not ready in time for the Magpies' first scheduled home national championship match in September.
New union chief executive Jay Campbell said there are enough weeks built into the drainage and turf replacement programme for the union to be confident the 16,000 capacity rugby and cricket stadium will be ready in time for the first home game in the Mitre 10 Cup championship, a week-three match against Counties Manukau on September 2.
He was speaking at the end of the first week of the $4.9 million Napier City Council project, disrupted by the falling of more than 40mm of rain but by yesterday, with most of the grass removed, apparently already ahead of schedule.
Read more: Council will not face fine over playing surface at McLean Park
Rugby bosses 'not happy' with McLean Park for tonight's Super match
After losing one day because of the rain — including 26.6mm on Tuesday (more than a metric inch) — the work resumed and continued during the weekend, including the increasing shuttle of about 1800 truck movements carting away excavated oval fill and replacing it with the base needed for the new drainage infrastructure and the laying of a new hybrid all-weather surface.