Napier CBD's $5.2 million drainage upgrade has more than two years of digging ahead of it to lessen the flood risk, says Napier City Council infrastructure director Jon Kingsford.
"Typically when you design for a stormwater drainage network you design for a one-in-ten-year event, but the network we are installing is for a one-in-50-year event," he said.
"That makes everything bigger - bigger pipes take longer to lay."
He said the highest point in the CBD was the foredune system "which creates some real difficulties when it comes to drainage".
Future street digging would only occur during "the quiet periods", outside of special events and holiday periods, and would be completed by the council's own team.