The Kererū Gorge culvert official reopening will be celebrated with a community event on April 17, 2025. Video / Hastings District Council
One major Hawke’s Bay roading rebuild project set to connect a rural community left isolated after Cyclone Gabrielle is nearing completion, while another has been pushed back.
The Kererū Gorge culvert structure is on track to be officially reopened on Thursday, April 17, with a community ceremony.
Meanwhile, the Puketapu Bridge is expected to be reopened inlate August, pushed back from late June to early July 2025.
The Kererū Gorge culvert structure (left) is on track to be officially reopened on Thursday, April 17, 2025.
The Puketapu bridge reopening has been pushed back until August 2025.
Craig Thew, Hastings District Council group manager of infrastructure, said the Kererū Gorge culvert contractor had been working six days a week to prepare the structure for the community opening.
“Pavement and structural works are underway, with shotcreting (spray concrete) for tie-ins to connect to the road, stream diversion, revegetation, final surfacing, guardrail installation, line-marking and signage all planned over the next three to four weeks.”
He said further work below the road level would continue for about six more weeks after the opening.
Thew said the project had come with challenging ground conditions that impacted the piled foundation, which required larger ‘digouts’ to reach solid ground.
The Kererū gorge culvert is scheduled to reopen on April 17. Photo / Peter Scott - Above Hawke’s Bay
“This, in turn has influenced the arch structure and the backfill weight needing to be reduced using expanded polystyrene blocks with additional steel reinforcing.”
He said delaying the Springfield Rd works until after the Puketapu Bridge completion would have cost ratepayers $80,000 due to lower NZTA subsidy rates after June 2025.
“There would also have been an additional $100,000 in costs to keep the road open and maintained in its current condition.
“Whilst public frustration is understandable, HDC does need to prioritise certain works to achieve value for money for our community,” Thew said.
Michaela Gower joined Hawke’s Bay Today in 2023 and is based out of the Hastings newsroom. She covers Dannevirke and Hawke’s Bay news and loves sharing stories about farming and rural communities.