The resurfacing of the roads around two of the district's roundabouts will be carried out over the last two weeks of this month.
Work on the Guthrie Rd and Nimmon St (Havelock North) roundabout will start this Friday and take just over a week, weather permitting.
Residents in the vicinity of the work have been advised and general road users are being asked to avoid the intersection if possible. While the roads will not be closed, there will be traffic management in place and there could be delays.
The second roundabout is in Mangateretere, at the intersection of Te Mata Mangateretere, Pilcher and Lawn Rds. That work started on Monday and is expected to be completed by January 27, weather permitting.
The Mangateretere project will require the closure of the intersection from Saturday, January 21, again weather permitting.