The Haumoana sea wall is on track for completion by mid-July, as long as big swells don't keep getting in the way.
Hastings District Council's director of major capital projects delivery Graeme Hansen said the $600,000, 100-metre seawall was approximately 70 per cent complete.
He added the stormy conditions over the weekend did not delay the work.
"The rain event on the weekend had no effect on the works," Hansen said.
"We did lose one week with the large sea event of the week of May 24 to 28."