It had been due for replacement in 2006 but inspections showed it was standing up well to the underwater conditions so had lasted a great deal longer.
Installing the new one will be a tricky operation.
Firstly almost one metre diameter pipes will be welded into two strings of 150m long. They will then be loaded onto rollers along Richmond Rd and inched over the stopbanks to the water's edge.
From there the first string will be towed out to sea using four boats and then slowly submerged so it is in the right place to be attached to the outfall pipe. The second diffuser pipe will then be towed out to the end of the first, and submerged.
The submersion is an intricate operation of its own; needing to be done slowly, allowing gentle angles to be maintained so there is no risk of the pipe being damaged.
Once the new pipe is in place, the contractors have a two hour window in which the wastewater plant can be switched off to allow the changeover to the new diffuser.
That will also not be easy, as there is little to no visibility for the divers in that area, because of very fine sediment that clouds the water.
The dive teams will practise on dry land "to get the hang of it", said council's wastewater manager, David James.
The work will mean that Richmond Rd will need to be closed at times during the construction of the diffuser, and for about five days as the pipe is moved to the sea edge.
That closure will also affect the cycleway along the top of the stopbank, and the bridle path on the seaward side of the stopbank. Alternative access ways and detours will be signposted.
Council asks that people show patience during this time, as staff and contractors work to enable the management of wastewater with as little disruption as possible.