Work beneath the Skinny Bridge at Matamau on the new crossing for the Whakaruatapu Stream near Dannevirke on SH2 is progressing well, despite the onset of winter.
The $6.8 million project began last November and is expected to take two years.
New Zealand Transport Agency contractors Stringfellows are building a corrugated steel-arched culvert and the reinforced concrete foundations for it have been poured in three sections, with each pour taking more than 70 truck-loads of concrete. The latest pour took place last Friday.
"Each section has been built in stages," David McGonigal, the NZTA highways manager, Central, said. "First the reinforcing steelwork is put in place, then the wooden formwork is built to act as a mould for the concrete. Once the concrete has hardened, the formwork is removed and the corrugated steel arch is formed and bolted into place.
"However, there is still much to do after the corrugated steel-arched culvert has been completed. The excavation and placing of more than 150,000m3 of earth will be the toughest part of the project. This is due to start in spring and the completion date is set for June next year."