Hawkes Bay Today
  • Hawke's Bay Today home
  • Latest news
  • Sport
  • Business
  • Opinion
  • Lifestyle
  • Property
  • Video
  • Death notices
  • Classifieds

Subscriptions

  • Herald Premium
  • Viva Premium
  • The Listener
  • BusinessDesk

Sections

  • Latest news
  • On The Up
  • Sport
  • Business
  • Opinion
  • Lifestyle
  • Property
    • All Property
    • Residential property listings
  • Rural
    • All Rural
    • Dairy farming
    • Sheep & beef farming
    • Horticulture
    • Animal health
    • Rural business
    • Rural life
    • Rural technology

Locations

  • Napier
  • Hastings
  • Havelock North
  • Central Hawke's Bay
  • Tararua

Media

  • Video
  • Photo galleries
  • Today's Paper - E-Editions
  • Photo sales
  • Classifieds

Weather

  • Napier
  • Hastings
  • Dannevirke
  • Gisborne

NZME Network

  • Advertise with NZME
  • OneRoof
  • Driven Car Guide
  • BusinessDesk
  • Newstalk ZB
  • Sunlive
  • ZM
  • The Hits
  • Coast
  • Radio Hauraki
  • The Alternative Commentary Collective
  • Gold
  • Flava
  • iHeart Radio
  • Hokonui
  • Radio Wanaka
  • iHeartCountry New Zealand
  • Restaurant Hub
  • NZME Events

SubscribeSign In
Advertisement
Advertise with NZME.
Home / Hawkes Bay Today

$620m Manawatū-to-Hawke’s Bay highway pushed back to mid-2025

RNZ
3 Apr, 2023 11:28 PM4 mins to read

Subscribe to listen

Access to Herald Premium articles require a Premium subscription. Subscribe now to listen.
Already a subscriber?  Sign in here

Listening to articles is free for open-access content—explore other articles or learn more about text-to-speech.
‌
Save

    Share this article

Grant Kauri says the new highway will now open in mid-2025. Photo / RNZ

Grant Kauri says the new highway will now open in mid-2025. Photo / RNZ

The opening date of the new highway between Manawatū and Hawke’s Bay has been delayed until mid-2025.

The $620 million replacement for the shut road through the Manawatū Gorge, Te Ahu a Turanga, was expected to be finished in late 2024.

But problems in the ground where foundations for two 300m bridges at the Palmerston North-Ashhurst end of the project, and Covid-19 complications, have pushed that back.

Since the old State Highway 3 through the gorge shut permanently because of rockfall in 2017, motorists travelling between the east and west of the lower North Island have been forced over the slow and windy Saddle Rd or Pahīatua Track.

Project alliance owner interface manager Grant Kauri confirmed the new expected opening date during a media tour of the construction site on Monday.

Advertisement
Advertise with NZME.
Advertisement
Advertise with NZME.

“We’re now looking at a time of mid-2025, primarily due to a lot of the challenges that we’ve faced across the project, [including] the high artesian water pressure and being unable to get a good start on our piling on bridge 2,” he said, having previously confirmed to RNZ the late-2024 opening date was under review.

“[And] Covid and the real impacts that’s had on us in terms of shutdown and supply chain issues — that commutative effect has pushed us out a further six months.”

It was too soon to say what effect the new date would have on the project’s cost, but that was under assessment, Kauri said.

Advertisement
Advertise with NZME.

Construction on the new 11.5km, four-lane road began more than two years ago after the region had waited for many years for a more resilient east-west route not affected by slips, as the gorge road was.

Problems under the piles for this bridge over a wetland are one of the reasons the new road's opening date has been delayed. Photo / RNZ
Problems under the piles for this bridge over a wetland are one of the reasons the new road's opening date has been delayed. Photo / RNZ

From the Palmerston North end, at Ashhurst, the new road wends over the two bridges, before climbing a steep cut in the lower Ruahine Range.

One bridge, an “eco-viaduct” over a wetland, had an unusually large amount of artesian groundwater where its piles went, Kauri said.

“We had to eliminate the water, because if we started piling when the water was still there it would just be coming out of the ground and make it unworkable.”

Huge 30-40m concrete spans were now appearing in place on the viaduct.

They were made in Napier and were hauled to the site in the early hours so as not to disrupt traffic, Kauri said.

The Parahaki Bridge over the Manawatū River also presented unexpected challenges where its piles went.

This structure would be among the final parts of the new road to finish, in early 2025, and would include a lookout for the shared bike and walking track next to the new road, Kauri said.

Its piers were undamaged during Cyclone Gabrielle, although there was minor damage to the temporary structures being used in its construction.

“With the water that’s coming from the other side, the Manawatū River was a natural funnel for a lot of that water to come through,” Kauri said.

Advertisement
Advertise with NZME.

“We experienced a high volume of water, the highest level since the 2004 floods.”

With that came debris — mostly logs, which caused the minor damage.

Further up the lower slopes of the Ruahine Range, the landscape is changing dramatically on the windy peaks that house a wind farm.

“Our total earthworks across the project are 6 million cubic metres,” Kauri said.

“We’ve moved just a scratch over 5.2 million cubic metres. We’re nearing the completion of these earthworks.”

He said they would be finished ahead of time.

Advertisement
Advertise with NZME.

The route carved out from a massive cut into the hillside is starting to look like a road.

“We’re doing pavement trials now, and also on the Ashhurst side you can see us building our pavement and getting that prepped up, making some good inroads there.”

The curving climb, below high terraces, looks like the Transmission Gully road north of Wellington, and it’s just as steep.

At the top among the turbines, “zone 3″ has also proved tricky in places due to the wetness of the ground, but the road’s path is clearly visible.

At the Hawke’s Bay-Woodville end, the road begins at the intersection of where the old SH3 meets the beginnings of Saddle Rd.

– RNZ

Advertisement
Advertise with NZME.
Save

    Share this article

Latest from Hawkes Bay Today

Hawkes Bay TodayUpdated

Taradale and Pirate set sail for Hawke's Bay club rugby final

05 Jul 11:55 PM
Premium
Hawkes Bay Today

Couple behind lauded cocktail bar call it a day: 'I don’t think people are prioritising social lives'

05 Jul 06:00 PM
Hawkes Bay Today

Flaxmere Woolworths site work begins, supermarket built by mid-2026

05 Jul 06:00 PM

There’s more to Hawai‘i than beaches and buffets – here’s how to see it differently

sponsored
Advertisement
Advertise with NZME.

Latest from Hawkes Bay Today

Taradale and Pirate set sail for Hawke's Bay club rugby final

Taradale and Pirate set sail for Hawke's Bay club rugby final

05 Jul 11:55 PM

Dominant first halves were the difference, with Maddison Trophy final spots on the line.

Premium
Couple behind lauded cocktail bar call it a day: 'I don’t think people are prioritising social lives'

Couple behind lauded cocktail bar call it a day: 'I don’t think people are prioritising social lives'

05 Jul 06:00 PM
Flaxmere Woolworths site work begins, supermarket built by mid-2026

Flaxmere Woolworths site work begins, supermarket built by mid-2026

05 Jul 06:00 PM
Premium
End of swimming pool weeds: Family's delight as cyclone-hit home gets green light

End of swimming pool weeds: Family's delight as cyclone-hit home gets green light

04 Jul 06:00 PM
From early mornings to easy living
sponsored

From early mornings to easy living

NZ Herald
  • About NZ Herald
  • Meet the journalists
  • Newsletters
  • Classifieds
  • Help & support
  • Contact us
  • House rules
  • Privacy Policy
  • Terms of use
  • Competition terms & conditions
  • Our use of AI
Subscriber Services
  • Hawke's Bay Today e-edition
  • Manage your print subscription
  • Manage your digital subscription
  • Subscribe to Herald Premium
  • Subscribe to the Hawke's Bay Today
  • Gift a subscription
  • Subscriber FAQs
  • Subscription terms & conditions
  • Promotions and subscriber benefits
NZME Network
  • Hawke's Bay Today
  • The New Zealand Herald
  • The Northland Age
  • The Northern Advocate
  • Waikato Herald
  • Bay of Plenty Times
  • Rotorua Daily Post
  • Whanganui Chronicle
  • Viva
  • NZ Listener
  • Newstalk ZB
  • BusinessDesk
  • OneRoof
  • Driven Car Guide
  • iHeart Radio
  • Restaurant Hub
NZME
  • NZME Events
  • About NZME
  • NZME careers
  • Advertise with NZME
  • Digital self-service advertising
  • Book your classified ad
  • Photo sales
  • © Copyright 2025 NZME Publishing Limited
TOP